
What
Does BLM Require In a Bond?
Costs must be estimated as if BLM
were hiring a contractor to perform all required
reclamation [43 CFR 3809.552(a)].
Costs must include the use of
off-site equipment as if the project area was vacated, and
they must include all associated mobilization and
demobilization costs {43 CFR 3809.554(a)].
The estimate must include when
applicable, all interim maintenance to maintain compliance
with applicable environmental requirements while contracts
are developed and executed [43 CFR 3809.552(a)].
The operator’s estimate must cover
all reclamation requirements in Notices and approved Plans
of Operation [43 CFR 3809.301(b), .401(d), .552(a), and 43
CFR 3809.1-3(d) for extended Notices]
The estimate must be accompanied by a worksheet
explaining how these costs were calculated.
Use actual disturbance dimensions, cubic feet of
material, length of time to complete the job, etc.
The operator’s estimate must
identify the relevant Operating and Maintenance cost
relating to reclamation including:
a. Equipment rental or acquisition costs
b. Equipment
operation costs
c. Equipment maintenance costs
d. Cost of operating supplies
e. Labor
costs for operations maintenance and supervision
f. Reclamation
materials acquisition costs.
The operator’s estimate must
include the Add-on costs as explained in the footnotes of
the Cost Estimate Summary Sheet.
These include:
1.
Where appropriate, the cost to BLM to develop an
Engineering, Design and Construction Plan for reclamation
should the operator not reclaim. (Implementation of the
reclamation plan)
2.
A contingency fund to cover unforeseen
circumstances related to the Engineering, Design and
Construction Plan.
3.
The prime contractor’s profit of approximately 10
percent of the estimated operation and maintenance costs.
4. The
contractor’s liability insurance premium equal to 1.5
percent of the estimated labor costs for the project with
estimated contract costs over $100,000.
5.
A set amount equal to 3 percent of the estimated
operation and maintenance costs for the payment of
premiums for both a performance bond and a payment bond as
required by the Miller Act with estimated contract costs
over $100,000 (40 U.S.C. 270 et seq.).
6.
BLM’s labor and operations cost for the Field and
State offices to administer the contract.
7.
BLM’s indirect costs (building rental
electricity, telephone, etc.)
Required by Washington Office IM 2003-011, October
8, 2002)
|